As you are probably by now aware, we are deep into construction season which means orange barrels, flaggers, and traffic delays but also the hope of nice new smooth road surfaces.  There are several projects going on right now in Mapleton.  UDOT is resurfacing Highway 89 from the south end of town up to approximately 1200 North.  This will include updating some pedestrian ramps, grinding the existing road surface and laying a brand new 2” overlay of asphalt.  Mapleton City is resurfacing several roads ranging from a full depth reclamation and rebuild to edge mill and 2” overlay.  The roads that will be affected over the next month or so are:

  • US89: US6 to 1200 NORTH
  • 1200 NORTH: MAIN STREET to 1000 EAST
  • 600 NORTH: 200 WEST to MAIN STREET
  • 300 WEST: MAPLE STREET to 600 NORTH
  • 800 WEST: MAPLE STREET to 800 SOUTH
  • 800 SOUTH: US89 to 1200 WEST
  • 1600 SOUTH: MAIN STREET to 800 EAST
  • 800 WEST: 1600 SOUTH to 2000 SOUTH
  • 2000 SOUTH: 800 WEST to MONTA VISTA DRIVE
  • PARK MEADOWS DRIVE: US89 to 2000 SOUTH
  • 2000 SOUTH: PARK MEADOWS DRIVE to 800 WEST
  • ELKVIEW CIRCLE
  • NORTH PARK PARKING LOT
  • IRA ALLEN PARK SOUTH PARKING LOT

Please be safe and courteous as you travel through work zones and we appreciate your patience as we work hard to improve Mapleton City Streets.  If you have any questions or concerns, please contact Public Works at 801-489-6253.

 

 

The Construction Project on US-89 has officially begun

The initial phase includes removing and replacing Pedestrian Ramps at various intersections along US-89. Please be cautious and courteous while driving through the work zone.

Looking Ahead

Starting on May 30th construction crews will begin rotomilling (removing) the top 1.5 inches of the road surface. This work will start at 1600 North and head South. After the rotomilling is complete, crews will overlay the freshly ground road with 2 inches of new asphalt.During this time, travel along portions of the road will be limited to a single lane with Flaggers directing traffic. Be prepared for delays of up to 15 minutes if you are traveling through the construction zone during working hours.

Keep in Mind

The contractor will maintain access to properties and side streets throughout the project. If your access is directly adjacent to US-89 you may experience temporary loss of access due to construction directly in front of your property. You will be notified before the contractor begins this work.The segment between 1600 N and 3000 S is expected to be completed by mid-June, with the southern end to be completed by fall of 2018One lane of traffic in each direction will remain open in most areas along SR-89 with traffic controls in place continuously.
Some areas will be restricted to a single lane with flaggers directing traffic during working hours. If you would like to receive updated information, please send a request to our project e-mail at: 3locations@utah.gov

Reminders

• Normal working hours will be 7 a.m. – 7 p.m., Monday – Saturday.
• Traffic may be restricted to a single lane.
• Expect noise, dust, pedestrian detours and inconvenience. There will be times of restricted access during construction.

Contact Information

For questions, concerns or e-mail updates, please contact the Public Information Team:

Hotline: 855-307-9363
E-mail: 3locations@utah.gov